Cause of construction delay - Theoretical framework

Research output: Chapter in Book/Report/Conference proceedingConference contribution

31 Citations (Scopus)

Abstract

Delay can be defined as time overrun or extension of time to complete the project. Construction delay is something that cannot avoided especially in government agencies in Malaysia. Therefore delay is a situation when the actual progress of a construction project is slower than the planned schedule or late completion of the projects. The causes of delay are taken from the pass literature review. There are two main type of delay: excusable delay and non-excusable delay. The literature reviews are summarized and the delay framework is constructed based on the literature review summary in context of public higher learning institution.

Original languageEnglish
Title of host publicationProcedia Engineering
Pages490-495
Number of pages6
Volume20
DOIs
Publication statusPublished - 2011
Event2nd International Building Control Conference, IBCC 2011 - Penang, Malaysia
Duration: 11 Jul 201112 Jul 2011

Other

Other2nd International Building Control Conference, IBCC 2011
CountryMalaysia
CityPenang
Period11/7/1112/7/11

Keywords

  • Construction delay
  • Factors
  • Public institution of higher learning

ASJC Scopus subject areas

  • Engineering(all)

Cite this

Cause of construction delay - Theoretical framework. / Hamzah, Noraini; Muhamad Azry, Khoiry; Arshad, Ishak; Mohd Tawil, Norngainy; Che Ani, Adi Irfan.

Procedia Engineering. Vol. 20 2011. p. 490-495.

Research output: Chapter in Book/Report/Conference proceedingConference contribution

Hamzah, N, Muhamad Azry, K, Arshad, I, Mohd Tawil, N & Che Ani, AI 2011, Cause of construction delay - Theoretical framework. in Procedia Engineering. vol. 20, pp. 490-495, 2nd International Building Control Conference, IBCC 2011, Penang, Malaysia, 11/7/11. https://doi.org/10.1016/j.proeng.2011.11.192
@inproceedings{c027fbd269f24cee94e23511f3cf654d,
title = "Cause of construction delay - Theoretical framework",
abstract = "Delay can be defined as time overrun or extension of time to complete the project. Construction delay is something that cannot avoided especially in government agencies in Malaysia. Therefore delay is a situation when the actual progress of a construction project is slower than the planned schedule or late completion of the projects. The causes of delay are taken from the pass literature review. There are two main type of delay: excusable delay and non-excusable delay. The literature reviews are summarized and the delay framework is constructed based on the literature review summary in context of public higher learning institution.",
keywords = "Construction delay, Factors, Public institution of higher learning",
author = "Noraini Hamzah and {Muhamad Azry}, Khoiry and Ishak Arshad and {Mohd Tawil}, Norngainy and {Che Ani}, {Adi Irfan}",
year = "2011",
doi = "10.1016/j.proeng.2011.11.192",
language = "English",
volume = "20",
pages = "490--495",
booktitle = "Procedia Engineering",

}

TY - GEN

T1 - Cause of construction delay - Theoretical framework

AU - Hamzah, Noraini

AU - Muhamad Azry, Khoiry

AU - Arshad, Ishak

AU - Mohd Tawil, Norngainy

AU - Che Ani, Adi Irfan

PY - 2011

Y1 - 2011

N2 - Delay can be defined as time overrun or extension of time to complete the project. Construction delay is something that cannot avoided especially in government agencies in Malaysia. Therefore delay is a situation when the actual progress of a construction project is slower than the planned schedule or late completion of the projects. The causes of delay are taken from the pass literature review. There are two main type of delay: excusable delay and non-excusable delay. The literature reviews are summarized and the delay framework is constructed based on the literature review summary in context of public higher learning institution.

AB - Delay can be defined as time overrun or extension of time to complete the project. Construction delay is something that cannot avoided especially in government agencies in Malaysia. Therefore delay is a situation when the actual progress of a construction project is slower than the planned schedule or late completion of the projects. The causes of delay are taken from the pass literature review. There are two main type of delay: excusable delay and non-excusable delay. The literature reviews are summarized and the delay framework is constructed based on the literature review summary in context of public higher learning institution.

KW - Construction delay

KW - Factors

KW - Public institution of higher learning

UR - http://www.scopus.com/inward/record.url?scp=84855715950&partnerID=8YFLogxK

UR - http://www.scopus.com/inward/citedby.url?scp=84855715950&partnerID=8YFLogxK

U2 - 10.1016/j.proeng.2011.11.192

DO - 10.1016/j.proeng.2011.11.192

M3 - Conference contribution

AN - SCOPUS:84855715950

VL - 20

SP - 490

EP - 495

BT - Procedia Engineering

ER -